   Weekly progress report as on 17.02.2012
    
  ROB at Parappanangady    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side In progress Done LHS 100%, RHS- 100%
  Dirt wall AP2 concreting  In progress Done 100%
  Dirt wall AP1 concreting  In progress Done 100%
  Handrail casting In progress 1400 nos completed.
  Handrail fixing In progress NH side 10 slab completed.
  Handrail fixing In progress CALICUT side 8 span over.
  Boring at RP4 & RP1 Completed PILING COMPLETED
  Boring at RP3 In progress 4-PILE CONCRETED
  Boring at RP2 In progress RP-3 two pile concreted.
  NH side RE panel erection In progress 100% completed.
  RE wall work calicut side. In progress 95% completed.
  expansion joint  In progress completed.
  painting-slab In progress 70% completed.
 
Back
 
    
POOJA BEFORE RAILWAY PILECAP EXCAVATION.

    
    
KITCO QUALITY INSPECTION.

    
    
EARTH FILLING RP2 LOCATION.

    
    
AP2 SIDE APPROACH WORK.

    
 
    
SERVICE ROAD WORK

    
    
REINFORCEMENT LOWERING IN RP3-5.

    
    
PILE CHIPPING IN RP1.

    
 
 
 

 

 

 

 

 

 

 