   Weekly progress report as on 17.02.2012
    

KORATTY ROB

PROGRESS REPORT (upto 17th February 2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location: All 5 pile concreted; Pile chipping in progress; PCC for Pile Cap Done

P8 location: Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 60%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

Pile cap, Trestle column, trestle beam at P7 location.

 

Awaiting the sanction from the railways for the staging & superstructure drawing.

 

 

 

 

 

 

 

 

             

WORKS PLANNED FOR THIS WEEK

P7 Pile Cap Concreting

 

 
Back
 
    
PCC FOR PILE CAP AT P7

    
    
P7 PILE CHIPPING.

    
    
P7 PILE CHIPPING.

    
    
P7 PCC 1

    
 
    
P7 EXCAVATION

      
 

 

 

 

 

 

 

 