   Weekly progress report as on 17.02.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaining for completion as per the weekly plan

Remarks

1

PILE Muthambi side

27

18

9

0

2

0

2

3

 

 

2

PILE Thamarassery side

33

30

3

0

0

0

0

0

 

 

3

PILE NH SIDE

30

30

0

0

0

0

0

0

 

 

4

PILE CAP Muthambi SIDE

9

6

3

0

0

0

0

0

 

 

5

PILE CAP Thamarassery SIDE

11

9

2

0

2

1

1

1

 

Work in progress.

6

PILE CAP NH SIDE

10

7

3

0

0

0

0

2

 

 

7

PIER Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

8

PIER Thamarassery SIDE

11

6

5

0

2

1

1

2

 

Work in progress.

9

PIER NH SIDE

10

7

3

0

0

0

0

0

 

 

10

PIER CAP Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

11

PIER CAP Thamarassery SIDE

11

0

11

0

1

0

1

1

 

 

12

PIER CAP NH SIDE

10

4

6

0

0

0

0

2

 

 

13

RE/R WALL Muthambi side

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

14

RE/R WALL Thamarassery side SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

15

RE/R WALL NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

16

BEAM/SLAB Muthambi SIDE

8

4

4

3

1

0

1

0

 

 

17

BEAM/SLAB Thamarassery SIDE

10

0

10

0

0

0

0

0

 

 

18

BEAM/SLAB NH SIDE

11

0

11

0

1

0

1

2

 

AP1-P1  girder reinforcement work completed concreting on 18.02.2012

19

HR/FP/KERB Muthambi SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

20

HR/FP/KERB thamarassery SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

21

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

23

Utility shifting

 

 

 

 

 

 

0

 

 

KSEB utility shifting started. Shifted 1 post 

 

Availbility of Men               
Date 02-11-2012 02-12-2012 13/2/2012 14/2/2012 15/2/2012 16/2/2012 17/2/2012
Nof labours 65 60 65 62 62 60 60 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 90 100
Fine Aggreagate(m3) 75 100
Cement(bag) 1500 2000
Steel(MT) 25 25 

 

 
Back
 
    
STEEL WORK FOR GIRDERS P1-P2

    
    
REINFORCEMENT WORK IN PROGRESS FOR GIRDER AP1-P1

    
    
PILE CAP CONCRETING P20

    
    
HAND RAIL CASTING IN PROGRESS

    
 
    
GIRDER CONCRETING P10-P11

      
 

 

 

 

 

 

 

 