   Weekly progress report as on 17.02.2012
    

WORK

STATUS

BALANCE

SHORNUR SIDE

HANDRAIL FIXING COMPLTED

NIL

EXPANSION JOINT

AP1 COMPLETED

NIL

APPROACH PORTION

APPROACH SLAB PCC COMPLETED

SLABCONCRETING, METALING, FOOTHPATH SLAB, INNER KERB

M.C SIDE

RCC WALL PORTION CONCRETE COMPLETED

NIL

OUTER KERB

COMPLETED 35 M ONE SIDE

50 MBALANCE

DRAINAGE SPOUT

IN PROGRESS

 

APPROACH SLAB

CONCRETE COMPLETED

 

HANDRAIL FIXING

YET TO START

 

PRECAST FOOTHPATH SLAB

CASTING IN PROGRESS

 

PAINTING WORKS

3 SLABS COMPLETED

  

 

Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RCC WALL SHORNUR SIDE 100% 80 20% 0 15.00% 6.00% 63.00% 15.00% 0 Handrail fixing in shornur sie approach portion complete.PCC for approach slab also completed.Metalling works,footpath slab work remaining.
10 RE/R WALL M.C SIDE 100% 78 22% 0 20.00% 7.00% 13.00% 20.00% 0 Friction slab concreting completed for a distance of 35 METRES on both sides.Outer kerb concreting completed for a distance of 35 metres.APPROACH SLAB CONCRETING completed.INNER KERB shuttering an reinforcement works in progress.
11 BEAM/SLAB SHORNUR SIDE 3 2 1 0 0 0 0 0 0 Cleaning of spans AP1,P1-P2 completed.Painting of two spans completed.
12 BEAM/SLAB M.C SIDE 12 11 1 0 1 1 0 0 0 Painting work of the beam and deck slab bottom are COMPLETEDD.ELEVEN   spans have been completed.
13 HR/FP/KERB SHORNUR  SIDE 100% 75 25% 0 8.00% 8.00% 0.00% 8.00% 0 days footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion completed 100%.
14 HR/FP/KERB M.C SIDE 100% 79 21% 0 10.00% 5.00% 6.00% 10.00%   .Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress.Deck slab cleaning in progress.PVC pipe laying in progress.DRAINAGE SPOUT commencement in M.C side.
15 BC/PAINTING 100% 30 70% 0 20.00% 8.00% 0.00% 20.00%   painting in progress .PAINTING OF DECK SLAB BOTTOM complete for 13 spans.
16 Deck Slab                    
17 Utility shifting                    
18 RCC WALL M.C SIDE 100% 55 45   30.00% 20.00%   30.00%   RCC wall concreting completed 100% on M.C side.outer kerb ,cornice completed 60% on RCC retainiing wall.Backfilling of soil also in progress. 
 
Back
 
    
RC WALL SHUTTERING MC SIDE

    
    
RC WALL CORNICE SHUTTERING IN MC SIDE 14-02-2012

    
    
PAINTING WORKS IN P3-P4 ON 17-02-2012

    
    
HANDRAIL POST IN KILA SIDE ON 14-02-2012

    
 
    
HAND RAIL SETTING

    
    
DRAINAGE SPOUT WORKS IN P12-P13 ON 12-02-2012

    
    
APPROACH SLAB IN MC SIDE ON 16-02-2012

    
 
 
 

 

 

 

 

 

 

 