Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
|
|
|
Completed |
|
|
|
2 |
PILE M.C SIDE |
36 |
36 |
|
|
|
Completed |
|
|
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
6 |
PIER M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
9 |
RCC WALL SHORNUR SIDE |
100% |
80 |
20% |
0 |
15.00% |
6.00% |
63.00% |
15.00% |
0 |
Handrail fixing in shornur sie approach portion complete.PCC for approach slab also completed.Metalling works,footpath slab work remaining. |
10 |
RE/R WALL M.C SIDE |
100% |
78 |
22% |
0 |
20.00% |
7.00% |
13.00% |
20.00% |
0 |
Friction slab concreting completed for a distance of 35 METRES on both sides.Outer kerb concreting completed for a distance of 35 metres.APPROACH SLAB CONCRETING completed.INNER KERB shuttering an reinforcement works in progress. |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
Cleaning of spans AP1,P1-P2 completed.Painting of two spans completed. |
12 |
BEAM/SLAB M.C SIDE |
12 |
11 |
1 |
0 |
1 |
1 |
0 |
0 |
0 |
Painting work of the beam and deck slab bottom are COMPLETEDD.ELEVEN spans have been completed. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
75 |
25% |
0 |
8.00% |
8.00% |
0.00% |
8.00% |
0 days |
footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion completed 100%. |
14 |
HR/FP/KERB M.C SIDE |
100% |
79 |
21% |
0 |
10.00% |
5.00% |
6.00% |
10.00% |
|
.Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress.Deck slab cleaning in progress.PVC pipe laying in progress.DRAINAGE SPOUT commencement in M.C side. |
15 |
BC/PAINTING |
100% |
30 |
70% |
0 |
20.00% |
8.00% |
0.00% |
20.00% |
|
painting in progress .PAINTING OF DECK SLAB BOTTOM complete for 13 spans. |
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
18 |
RCC WALL M.C SIDE |
100% |
55 |
45 |
|
30.00% |
20.00% |
|
30.00% |
|
RCC wall concreting completed 100% on M.C side.outer kerb ,cornice completed 60% on RCC retainiing wall.Backfilling of soil also in progress. |