   Weekly progress report as on 17.02.2012
    
 
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE KAINATTY  SIDE 18 18 0 0 0 0 0 0    
2 PILE NADAPURAM SIDE 27 27 0 0 0 0 0 0    
3 PILE CAP KAINATTY SIDE 6 6 0 0 0 0 0 0    
4 PILE CAP  NADAPURAM SIDE 9 9 0 0 0 0 0 0    
  PIER KAINATTY  SIDE 6 6 0 0 0 0 0 0    
6 PIER NADAPURAM SIDE 9 9 0 0 0 0 0 0    
7 PIER CAP KAINATTY  SIDE 6 6 0 0 0 0 0 0    
8 PIER CAP NADAPURAM SIDE 9 9 0 0 0 0 0 0    
11 RE/R WALL KAINATTY  SIDE 100% 95% 5% 5% 15.00% 10.00% 5.00% 3.00%   Friction slab.
10 RE/R WALL NADAPURAM SIDE 100% 95% 5% 5% 15.00% 10.00% 5.00% 3.00%   Friction slab.
12 BEAM/SLAB  Staging Kainatty side 6 5 1 1 1 1 1 0    
13 BEAM/SLAB  Bar bending and Fixing Kainatty side 6 5 1 1 1 1 1 0    
14 BEAM/SLAB  Shuttering  and Concreting  Kainatty side 6 5 1 1 1 0 1 1    
15 BEAM/SLAB  Staging Nadapuram side 9 8 1 1 0 0 1 0    
16 BEAM/SLAB  Bar bending and Fixing Nadapuram side 9 8 1 1 1 1 1 1   P6-P7 girder completed.
17 BEAM/SLAB  Shuttering  and Concreting  Nadapuram side 9 8 1 1 1 0* 1 1   P6-P7 girder completed.
18 BEAM/SLAB KAINATTY  SIDE 6 5 1 1 1 1 1 0    
19 BEAM/SLAB NADAPURAM SIDE 9 8 1 1 1 1 2 1   Steel work for P6-P7 slab in progress.
20 HR/FP/KERB KAINATTY  SIDE 100% 99% 1% 1% 50.00% 49.00% 1.00% 1.00%    
21 HR/FP/KERB NADAPURAM SIDE 100% 99% 1% 1% 10.00% 10.00% 1.00% 1.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men                 
Date   02-11-2011 02-12-2012 13-02-12 14-02-12 15-02-12 16-02-12 17-02-12
Nof labours   29 29 29 29 29 29 29 

 

 

Material Stocking Status Required Available
     
Fine Aggreagate(m3) 10 10
Cement(bag) 100 850
Steel(MT) 2 3
Coarse Aggreagate (m3) 12 12 

 

Utility shifting  
Utilities to be shifted Status
BSNL in progress
KSEB shifted
KWA shifted
Others shifted 

 

 

 

 
Back
 
    
STACK OF STONES FOR ROAD WORK

    
    
KERB AT KAINATTY SIDE RE WALL

    
    
EXCAVATION FOR FRICTIONS

    
    
CLEANING DECK SLAB FOR MASTI

    
 
    
KERB AT NADAPURAM SIDE

      
 

 

 

 

 

 

 

 