Prevoius Weekly Reports

   Weekly progress report as on 10.02.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 27 Completed    
2 PILE PADANNA SIDE 24 21 3 2 2 0 2 3    
3 PILE CAP CHERUVATHOOR SIDE 9 7 2 1 1 1 0 1   P9 Pile cap complete
4 PILE CAP  PADANNA SIDE 8 7 1 0 0 0 0 0    
5 PIER CHERUVATHOOR SIDE 9 6 3 0 0 0 0 2    
6 PIER PADANNA SIDE 8 7 1 0 0 0 0 0    
7 PIER CAP CHERUVATHOOR SIDE 9 5 4 1 0 0 1 0    
8 PIER CAP PADANNA SIDE 8 4 4 0 0 0 0 2    
9 RE/R WALL CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   RE panel 90 nos casting complete,Retaining wall excavation started,PCC complete for 15 m
10 RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 4 5 0 0 0 0 0    
12 BEAM/SLAB PADANNA SIDE 8 0 8 1 1 0 1 2   P1-P2 and P2-P3 girder & slab planned for next week
13 HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

Availbility of Men               
Date 04-02-2012 05-02-2012 06-02-2012 07-02-2012 08-02-2012 09-02-2012 10-02-2012
No of labours 61 73 73 73 73 73 73 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) shortage at site  
Fine Aggreagate(m3) shortage at site  
Cement(bag) 1600 2000
Steel(MT) 15 22 

 

Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1 locationclearedfor piling,P10 shifting complete,cables at approach portion to be shifted
KSEB in progress estimation yet to be received.No shifting works without prior payment.
KWA currently can be managed at site        

 

  AREAS OF  CONCERN AND CORRECTIVE ACTION:              
                     
1 P9 building demolition complete.  
                     
2 Land acquisition at AP1(BSNL) not yet done.At Padanna side, no workfront after PI location .
  BSNL Compound wall has been demolished.Piling at AP1 in progress.            
                     
3 KSEB informed that no shifting works will be done without prior payment.This may badly affect the progress of work.  

 

 
Back
 
    
VIEW FROM CHERUVATHUR SIDE

    
    
RETAINING WALL PCC AT CHERUVATHUR SIDE

    
    
P10 PILE CAP REINF IP

    
    
P9 PILE CAP COMPLETE

    
 
    
BORING AT API LOCATION

      
 

 

 

 

 

 

 

 