Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7886912
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly Progress report as on 10.02.2012
    
Sl No  Activity Description  Total Quantity Cumulative progress upto 9.2.12 Balance  work up to 9.2.12 Cumulative delay in Qty up to 9.2.12 Work  planned  during the week  Actual work done during the week  Delay in Qty up to this week Work  Planned for next week 
1 PILE  Pettah side(Approach portion) 12 12 0 0 0 0 0 0
2 PILE Anayara side(Approach portion) 12 12 0 0 0 0 0 0
3 PILE CAP Pettah side(Approach portion) 4 4 0 0 0 0 0 0
4 PILE CAP Anayara side(Approach portion) 4 4 0 0 0 0 0 0
5 PIER Pettah side(Approach portion) 4 4 0 0 0 0 0 0
6 PIER Anayara side(Approach portion) 4 4 0 0 0 1 0 0
7 PIER  CAP Pettah side(Approach portion) 4 3 1 1 1 1 0 1
  PIER  CAP Anayara side(Approach portion) 4 2 2 1 1 0 0 1
8 GIRDER Pettah side(Approach portion) 4   4          
9 GIRDER Anayara side(Approach portion) 4   4          
10 Service Road Pettah side(Approach portion) 1400 350 1050          
11 Service Road Anayara side(Approach portion) 1400 350 1050          
                   
 
Back
 
    
RT WALL PETTAH SIDE

    
    
PIERCAP P4

    
    
PIER P3-II

      
 

 

 

 

 

 

 

 

Untitled Document