Prevoius Weekly Reports

   24-11-2009
    

ROB at Koratty

 

Details of work done between 16th to 21st Nov 2009.

 

PROGRESS AS ON 21-11-2009
Work Planned upto 21/11/2009 Completed/Progress Delay
P3 pier cap Reinforcement works Completed 1 week due to perunnal
Shuttering work In progress  
Reinforcement work for I Girder In progress  
Approval of GAD by railways- follow up to be    
done by contractor    
Re wall in Koratty side  
Stopped for want of area, can
be started after the
construction of under pass.

 

 