   Weekly Progress report as on 10.02.2012
    

KORATTY ROB

PROGRESS REPORT (upto 10th February  2012)

RAILWAY PORTION

Total scope: 4 Locations

 

 

LOCATIONS:P1,P7  ,P8,P2

P1,P7 –N.H side

P8,P2-Pulikkakadavu side.

Total Piles: 18

 

No of PILES IN EACH LOCATION

P1 location: 4

P7 location:5

P8 location:5

P2 location:4

 

WORK COMPLETED IN EACH LOCATION OF RAILWAY PORTION

P1 location:Piling completed (4 piles),pile cap,trestle column,trestle beam.

P7 location:4 pile concreted upto last week,1 pile concreted on 7th feb 2012.

P8 location:Piling completed(5 piles),pile cap,Trestle column,trestle beam

P2 location:Piling completed(4 piles),pile cap,trestle column,trestle beam.

 

Approach portion at N.H side completed 60%

 

WORK COMPLETED AT PULIKKAKADAVU SIDE

All deck slab concreting completed at pulikkakadavu side.

Works completed upto the roadworks,miscellaneous works, in the approach portion at pulikkakadavu side.

WORKS BALANCE

P1-P7 superstructure (RCC structure)

P7-P8 superstructure( CENTRAL SPAN)

P8-P2 superstructure (RCC structure)

Pile cap,Trestle column,trestle beam at P7 location.

 

Awaiting the sanction from the railways for the superstructure drawing.

 

 

 

 

 

 

             

WORKS PLANNED FOR THIS WEEK

Earthwork excavation for pile chipping and pile cap concreting at P7

 

 
Back
 
    
RIG DISMATNLING WORK COMPLETED.

    
    
RIG DISMANTLING AT N.H SIDE USING HYDRA

    
    
CONCRETING OF THE PILE P7B3 COMPLETED AT N.H SIDE

      
 

 

 

 

 

 

 

 