   Weekly progress report as on 10.02.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RCC WALL SHORNUR SIDE

100%

75

25%

0

20.00%

3.00%

63.00%

15.00%

0

Concreting of outer  kerb and cornice completed on two sides. Soil filling completed upto 100%.Handrail fixing in progress.Expansion joint work in progress at AP1

10

RE/R WALL M.C SIDE

100%

78

22%

0

25.00%

17.00%

13.00%

20.00%

0

Friction slab concreting completed for a distance of 30 METRES on both sides.Outer kerb concreting completed for a distance of 30 metres.

11

BEAM/SLAB SHORNUR SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

Painting work of the beam and deck slab bottom are in progress.SEVEN  spans have been completed.

13

HR/FP/KERB SHORNUR  SIDE

100%

68

32%

0

0.00%

0.00%

0.00%

0.00%

0 days

footpath slab(P1-P2 )completed and AP1-P1 completed.Handrail fixing at the approach portion in progress.

14

HR/FP/KERB M.C SIDE

100%

79

21%

0

10.00%

5.00%

6.00%

10.00%

 

.Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress.Deck slab cleaning in progress.PVC pipe laying in progress.

15

BC/PAINTING

100%

30

70%

0

20.00%

8.00%

0.00%

20.00%

 

painting in progress .SEVEN spans completed. 

 

Availbility of Men               
Date 02-04-2012 02-05-2012 02-06-2012 02-07-2012 02-08-2012 02-09-2012 02-10-2012
Nof labours 33 34 34 35 35 35 34
               
Material Stocking Status              
  Required Available Remarks        
Fine aggregate {cft} 300 356          
Cement(bag) 450 55 stock will be replendished        
Steel inT 5.75 5.5 stock will be replendished        
Coarse Aggreagate (cft) 300 325          

 

Utility shifting

 

Utilities to be shifted

 

BSNL

COMPLETED

KSEB

COMPLETED

KWA

COMPLETED

Others

COMPLETED 

 

 