   Weekly progress report as on 03.02.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

26

1

0

1

1

0

0

 

 

2

PILE PADANNA SIDE

24

21

3

2

2

0

2

2

 

 

3

PILE CAP CHERUVATHOOR SIDE

9

7

2

1

1

0

1

1

 

 

4

PILE CAP  PADANNA SIDE

8

7

1

0

0

0

0

0

 

 

5

PIER CHERUVATHOOR SIDE

9

6

3

0

0

0

0

0

 

 

6

PIER PADANNA SIDE

8

7

1

3

1

1

0

0

 

P5 2nd lift complete

7

PIER CAP CHERUVATHOOR SIDE

9

5

4

1

0

0

1

0

 

 

8

PIER CAP PADANNA SIDE

8

3

5

0

1

1

0

0

 

P4 Pier cap complete

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

RE panel 40 nos casting complete,Retaining wall excavation started

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

3

6

0

1

1

0

0

 

P13-P12 girder and deck slab complete

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

1

0

1

1

 

P1-P2 and P2-P3 girder planned for next week

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 28-01-2012 29-01-2012 30-01-2012 31-01-2012 01-02-2012 02-02-2012 03-02-2012
No of labours 65 65 52 52 52 52 52 

 

Material Stocking Status Required Available Remarks  
Coarse Aggreagate (m3) available      
Fine Aggreagate(m3) available      
Cement(bag) 850 2200    
Steel(MT) 20 25    
         
         
Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1 to be shifted,local cable shifting complete at AP1,P10 shifting complete
KSEB in progress estimation yet to be received,works at cheruvathur side IP
KWA currently can be managed at site        

 

 

AREAS OF  CONCERN AND CORRECTIVE ACTION:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1

P9 building demolition complete.

 

2

Land acquisition at AP1(BSNL) not yet done.At Padanna side, no workfront after PI location .Piling at AP1 pending.

3

BSNL cables to be shifted at AP1 location.Compound wall needs to be demolished at AP1 for piling.Procedure in progress.

 

 

BSNL local cables shifting 90% complete at AP1.

 

 

 

 

 

 

 

 

Water Authority pipe line shifted.

 

 

 

 

 

 

 

 

 

 

 
Back
 
    
RE PANEL CASTING IP

    
    
P13-P12 DECK SLAB CONCRETE

    
    
P10 PILE CHIPPING COMPLETE

    
    
P7 AND P6 PIERS

    
 
    
P4 PIER CAP AND P5 PIER COMPLETE

    
    
P1-P2 GIRDER REINF IP

    
    
AP1 LOCATION

    
 
 
 

 

 

 

 

 

 

 