   Weekly progress report as on 03.02.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Piles 63 48 15   6 6   6
2 Pile cap at Kanjipura side 10 9 1 1 2 1 1 1
3 Pile Cap at Kuttipuram side 11 - 11 - - - - 2
3 Pier at Kanjipura side 9 8 1   1 1 - -
4 PierCap at Kanjipura side 9 2 7 -- 2 2 -- 2
5 PierCap at Kuttipuram side 10 -- 10 -- -- -- -- --
                   
Date 28/01/2012 30/01/2012 31/01/2012 02-01-2012 02-02-2012 02-03-2012      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 42 42 42 42 42 42      
                -  
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 55 m3 10 m3              
Coarse Aggregate  110 m3 25 m3              
Cement 900 bags 50 Bags              
Steel 7MT 15 MT              
 
Back
 
    
PILE P1B

    
    
PILE CAP P19

    
    
PIER CAP P18

      
 

 

 

 

 

 

 

 