   Weekly progress report as on 03.02.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  CALICUT  SIDE 48 48 0 0 0 0 1 0    
2 PILE THIRUR SIDE 24 24 0 0 0 0 11 0    
3 PILE CAP CALICUT  SIDE 12 12 0 0 0 0 1 0    
4 PILE CAP  THIRURSIDE 6 4 2 0 2 0 4 1    
5 PIER CALICUT SIDE 12 12 0 0 0 0 1 0    
6 PIER THIRUR SIDE 6 3 3 0 1 1 0 1    
7 PIER CAPCALICUT   SIDE 12 11 1 0 1 1 2 0   staging @ p5,p6 completed
8 PIER CAP THIRUR SIDE 6 3 3 0 0 0 0 2    
9 RE/R WALL CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
11 BEAM/SLAB CALICUT   SIDE 12 0 12 0 0 0 0 1    
12 BEAM/SLAB THIRUR SIDE 6 0 6 0 0 0 0 0    
13 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
16 Deck Slab                    
17 Utility shifting                    
                       
                       
                       
  Availbility of Men                   
  Date 28-01-2012 29-01-2012 30-01-2012 31-01-2012 01-02-2012 02-02-2012 03-02-2012      
  Nof labours 40 40 40 38 42 42 42      
                       
  Material Stocking Status Required Available Remarks              
  Coarse Aggreagate (m3) 28 21                
  Fine Aggreagate(m3) 18 10                
  Cement(bag) 450 190                
  Steel(MT)   16                
                       
                       
  Utility shifting                    
  Utilities to be shifted Status Remarks                
  BSNL shifting completed                  
  KSEB shifting in progress                  
  KWA shifting completed                  
  Others                    
                       
 