   Weekly progress report as on 03.02.2012
    
 
Si No  Activity Description  Total Quantity Cumulative progress upto 02.02.12 Balance  work up to 02.02.12 Cumulative delay in Qty up to 02.02.12 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 30 12 0 9 6 3 9   Pipe line broken on 26.01.12 at 2.20 am while boring.Repaired on 26.01.12
4 PILE vytilla side(railway portion) 6 1 5 0 1 0 1 0   RP1 P4 done . RP1 P5 was abandoned due to pile choking. Pile layout to be redesigned. 
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0   KWA line to be shifted. Will be over by 18.01.12. work completed on 23.01.12.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 2 7 0 0 0 0 2   P1,  P2
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 2 2   P15, P14, A2, P13, P12, P11, P10
14 GIRDER Palarivattom side(Approach portion) 7 5 2 0 1 1 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10
15 DECK SLAB Palarivattom side(Approach portion) 7 3 4 0 1 1 0 1   A2 P15, P15 P14, P14 P13
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
17 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0    
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
19 RE WALL PANEL 355 355 0 0 0 1 0 0 0  

 

Labour Report                    
                     
Date 27.01.12 28.01.12 29.01.12 30.01.12 31.01.12 01.02.12 02.02.12      
Day Fri Sat Sun Mon Tue Wed Thurs      
Climate sunny  sunny  sunny  sunny  sunny  sunny   sunny       
No.of labours 91 83 28 80 81 81 80      
                     
                     
Availability of Material                     
                     
Materials Required for week ending on 09.01.12 Available as on 03.02.12                
Fine aggregate(M3) Ready Mix Concrete                
Coarse aggregate(M3)                
Cement(BAG)                
Steel(TONN) 13 42                
                     
                     
 
Back
 
    
PILE CONCRETING AT P8

    
    
PILE CAP P1 CONCRETING

    
    
DECK CONCRETING P14 P13

      
 

 

 

 

 

 

 

 