Work Planned upto 05.12.2009 |
Completed/Progress |
Delay |
P3 pier cap Concreting works |
Completed |
1 week due to perunnal |
Reinforcement work for I Girder |
In progress |
|
Approval of GAD by railways- follow up to be done by contractor |
|
Delay in GAD approval |
Re wall in Koratty side-Stopped for want of area,
can be started after the construction of under |
|
Delay by the contractor in starting
under pass |