Prevoius Weekly Reports

   Weekly progress reprot as on 03.02.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaining for completion as per the weekly plan

Remarks

1

PILE Muthambi side

27

18

9

0

2

0

2

2

 

 

2

PILE Thamarassery side

33

30

3

0

0

0

0

0

 

 

3

PILE NH SIDE

30

27

3

0

2

2

0

1

 

 

4

PILE CAP Muthambi SIDE

9

6

3

0

0

0

0

0

 

 

5

PILE CAP Thamarassery SIDE

11

4

7

0

4

2

2

2

 

Work in progress.

6

PILE CAP NH SIDE

10

7

3

0

0

0

0

0

 

 

7

PIER Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

8

PIER Thamarassery SIDE

11

2

9

0

3

3

0

2

 

Work in progress.

9

PIER NH SIDE

10

7

3

0

0

0

0

0

 

 

10

PIER CAP Muthambi  SIDE

9

6

3

0

0

0

0

0

 

 

11

PIER CAP Thamarassery SIDE

11

0

11

0

2

0

2

1

 

 

12

PIER CAP NH SIDE

10

4

6

0

1

0

1

1

 

 

13

RE/R WALL Muthambi side

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

14

RE/R WALL Thamarassery side SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

15

RE/R WALL NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

16

BEAM/SLAB Muthambi SIDE

8

2

6

3

2

1

1

1

 

P10-P11 girder reinforcement work completed concreting on 06.02.2012

17

BEAM/SLAB Thamarassery SIDE

10

0

10

0

0

0

0

0

 

 

18

BEAM/SLAB NH SIDE

11

0

11

0

0

0

0

1

 

 

19

HR/FP/KERB Muthambi SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

20

HR/FP/KERB thamarassery SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

21

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

 

23

Utility shifting

 

 

 

 

 

 

0

 

 

KSEB utility shifting started. Shifted 1 post 

 

Availbility of Men               
Date 28/1/2012 29/1/2012 30/1/2012 31/1/2012 02-01-2012 02-02-2012 02-03-2012
Nof labours 62 65 65 70 60 60 60 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 90 115
Fine Aggreagate(m3) 90 110
Cement(bag) 1000 1250
Steel(MT) 20 25 

 

 
Back
 
    
REINFORCEMENT FOR PILE P9C

    
    
PILING IN PROGRESS AT P9C

    
    
PILE CHIPPING FOR P23

    
    
P10-P11

    
 
    
DECK SLAB P12-P13

      
 

 

 

 

 

 

 

 