Si No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
No of days remaing for completion as per the weekly plan |
Remarks |
1 |
PILE SHORNUR SIDE |
9 |
9 |
|
|
|
Completed |
|
|
|
2 |
PILE M.C SIDE |
36 |
36 |
|
|
|
Completed |
|
|
|
|
3 |
PILE CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
4 |
PILE CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
5 |
PIER SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
6 |
PIER M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
7 |
PIER CAP SHORNUR SIDE |
3 |
3 |
|
|
|
Completed |
|
|
|
|
8 |
PIER CAP M.C SIDE |
12 |
12 |
|
|
|
Completed |
|
|
|
|
9 |
RCC WALL SHORNUR SIDE |
100% |
75 |
25% |
0 |
20.00% |
8.00% |
63.00% |
20.00% |
0 |
Concreting of outer kerb and cornice completed on two sides of rcc wall .Soil filling and roadworks planned for next week. |
10 |
RE/R WALL M.C SIDE |
100% |
63 |
35% |
0 |
25.00% |
15.00% |
13.00% |
25.00% |
0 |
Friction slab concreting completed for a distance of 25 metres on both sides of RE wall.0uter kerb concreting completed 25 metres |
11 |
BEAM/SLAB SHORNUR SIDE |
3 |
2 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
|
12 |
BEAM/SLAB M.C SIDE |
12 |
11 |
1 |
0 |
1 |
1 |
0 |
0 |
0 |
Painting work of the beam and deck slab bottom are in progress.SEVEN spans have been completed. |
13 |
HR/FP/KERB SHORNUR SIDE |
100% |
62 |
38% |
0 |
0.00% |
0.00% |
0.00% |
0.00% |
0 days |
footpath slab(P1-P2 )completed. |
14 |
HR/FP/KERB M.C SIDE |
100% |
59 |
41% |
0 |
10.00% |
2.00% |
6.00% |
10.00% |
|
.Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress. |
15 |
BC/PAINTING |
100% |
20 |
80% |
0 |
20.00% |
7.00% |
0.00% |
20.00% |
|
painting in progress .SEVEN spans completed. |
16 |
Deck Slab |
|
|
|
|
|
|
|
|
|
|
17 |
Utility shifting |
|
|
|
|
|
|
|
|
|
|
18 |
RCC WALL M.C SIDE |
100% |
22 |
78 |
|
30.00% |
22.00% |
|
30.00% |
|
RCC wall concreting completed on 50 metres(running metres).RCC wall shuttering for the balance works in progress. |