Prevoius Weekly Reports

   Weekly progress report as on 03.02.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE SHORNUR  SIDE 9 9       Completed      
2 PILE M.C SIDE 36 36       Completed        
3 PILE CAP SHORNUR SIDE 3 3       Completed        
4 PILE CAP  M.C SIDE 12 12       Completed        
5 PIER SHORNUR  SIDE 3 3       Completed        
6 PIER M.C SIDE 12 12       Completed        
7 PIER CAP SHORNUR  SIDE 3 3       Completed        
8 PIER CAP M.C SIDE 12 12       Completed        
9 RCC WALL SHORNUR SIDE 100% 75 25% 0 20.00% 8.00% 63.00% 20.00% 0 Concreting of outer  kerb and cornice completed on two sides of rcc wall .Soil filling and roadworks planned for next week.
10 RE/R WALL M.C SIDE 100% 63 35% 0 25.00% 15.00% 13.00% 25.00% 0 Friction slab concreting completed for a distance of 25 metres on both sides of RE wall.0uter kerb concreting completed 25 metres
11 BEAM/SLAB SHORNUR SIDE 3 2 1 0 0 0 0 0 0  
12 BEAM/SLAB M.C SIDE 12 11 1 0 1 1 0 0 0 Painting work of the beam and deck slab bottom are in progress.SEVEN  spans have been completed.
13 HR/FP/KERB SHORNUR  SIDE 100% 62 38% 0 0.00% 0.00% 0.00% 0.00% 0 days footpath slab(P1-P2 )completed.
14 HR/FP/KERB M.C SIDE 100% 59 41% 0 10.00% 2.00% 6.00% 10.00%   .Footpath slab concreting completed in 11 spans.Precast footpath slab settings are in progress.
15 BC/PAINTING 100% 20 80% 0 20.00% 7.00% 0.00% 20.00%   painting in progress .SEVEN spans completed.
16 Deck Slab                    
17 Utility shifting                    
18 RCC WALL M.C SIDE 100% 22 78   30.00% 22.00%   30.00%   RCC wall concreting completed on 50 metres(running metres).RCC wall shuttering for the balance works in progress. 

 

Availbility of Men             
Date 28-1-2012 29-1-2012 30-1-2012 31-1-2012 02-01-2012 02-02-2012
Nof labours 28 27 27 28 28 33 

 

Material Stocking Status          
  Required Available Remarks    
Fine aggregate {cft} 300 356      
Cement(bag) 450 45 stock will be replendished    
Steel inT 5.75 6      
Coarse Aggreagate (cft) 300 325      

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 