Prevoius Weekly Reports

   Weekly progress report as on 27.01.2012
    
   
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaining for completion as per the weekly plan Remarks 
1 PILE Muthambi side 27 18 9 0 3 0 3 2    
2 PILE Thamarassery side 33 30 3 0 0 0 0 0    
3 PILE NH SIDE 30 27 3 0 0 0 0 2    
4 PILE CAP Muthambi SIDE 9 6 3 0 0 0 0 0    
5 PILE CAP Thamarassery SIDE 11 2 9 0 4 2 2 4   Work in progress.
6 PILE CAP NH SIDE 10 7 3 0 0 0 0 0    
7 PIER Muthambi  SIDE 9 6 3 0 0 0 0 0    
8 PIER Thamarassery SIDE 11 0 11 0 3 2 1 3   Work in progress.
9 PIER NH SIDE 10 7 3 0 0 0 0 0    
10 PIER CAP Muthambi  SIDE 9 6 3 0 0 0 0 0    
11 PIER CAP Thamarassery SIDE 11 0 11 0 0 0 0 2    
12 PIER CAP NH SIDE 10 3 7 0 2 1 1 1    
13 RE/R WALL Muthambi side 100% 0 100% 0 0.00% 0.00% 0 0.00%    
14 RE/R WALL Thamarassery side SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
15 RE/R WALL NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
16 BEAM/SLAB Muthambi SIDE 8 2 6 3 2 0 2 2   P12-P13 girder reinforcement work completed concreting on 28.01.2012
17 BEAM/SLAB Thamarassery SIDE 10 0 10 0 0 0 0 0    
18 BEAM/SLAB NH SIDE 11 0 11 0 0 0 0 0    
19 HR/FP/KERB Muthambi SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
20 HR/FP/KERB thamarassery SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
21 HR/FP/KERB NH SIDE 100% 0 100% 0 0.00% 0.00% 0 0.00%    
22 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0 0.00%    
23 Utility shifting             0     KSEB utility shifting started. Shifted 1 post 

 

Availbility of Men               
Date 21/1/2012 22/1/2012 23/1/2012 24/1/2012 25/1/2012 26/1/2012 27/1/2012
Nof labours 60 65 65 70 70 55 65 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 100 125
Fine Aggreagate(m3) 100 125
Cement(bag) 1000 1500
Steel(MT) 20 25 

 

 
Back
 
    
SIDE VIEW P13-P14-P15

    
    
REINFORCEMENT WORK IN PROGRESS PILE CAP P 24

    
    
PILE CHIPPING IN PROGRESS AT P22

    
    
PILE CAP P27 READY FOR CONCRETING

    
 
    
DECK SLAB CONCRETING P13-P14

    
    
DECK P13-P14

      
 

 

 

 

 

 

 

 