   Weekly progress report as on 27.01.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE CHERUVATHOOR  SIDE 27 24 3 2 2 2 0 1    
2 PILE PADANNA SIDE 24 21 3 3 0 0 3 2    
3 PILE CAP CHERUVATHOOR SIDE 9 7 2 0 1 0 1 1    
4 PILE CAP  PADANNA SIDE 8 7 1 0 0 0 0 0   P1 Pile cap complete
5 PIER CHERUVATHOOR SIDE 9 6 3 0 0 0 0 0    
6 PIER PADANNA SIDE 8 3.5 4.5 3 2 4 0.5 1   P6,P4and P1 Piers complete,P7 2nd lift complete
7 PIER CAP CHERUVATHOOR SIDE 9 5 4 1 0 0 1 0    
8 PIER CAP PADANNA SIDE 8 2 6 0 1 1 0 1   P1 Pier cap complete
9 RE/R WALL CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
10 RE/R WALL PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%   RE panel casting started
11 BEAM/SLAB CHERUVATHOOR  SIDE 9 3 6 0 1 0 1 1   P13-P12 girder shuttering complete
12 BEAM/SLAB PADANNA SIDE 8 0 8 0 0.5 0 0.5 1    
13 HR/FP/KERB CHERUVATHOOR  SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
14 HR/FP/KERB PADANNA SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%    
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%     

 

 

Availbility of Men                 
Date 20-01-2012 21-01-2012 22-01-2012 23-01-2012 24-01-2012 25-01-2012 26-01-2012 27-01-2012
No of labours 65 65 65 65 60 65 40 65 

 

Material Stocking Status Required Available Remarks
Coarse Aggreagate (m3) available    
Fine Aggreagate(m3) available    
Cement(bag) 750 100 shortage
Steel(MT) 15 30   

 

Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1 to be shifted.P10 shifting complete
KSEB in progress estimation yet to be received,P1 and P10 location cleared.
KWA currently can be managed at site        

 

  AREAS OF  CONCERN AND CORRECTIVE ACTION:              
                     
1 P9 building demolition complete.  
                     
2 Land acquisition at AP1(BSNL) not yet done.At Padanna side, no workfront after PI location .Piling at AP1 pending.
                     
3 BSNL cables to be shifted at AP1 location.Compound wall needs to be demolished at AP1 for piling.Procedure in progress.  
 
Back
 
    
RE PANEL CASTING IP

    
    
P13-P12 GIRDER SHUTTERING COMPLETE

    
    
P6 AND P7 PIERS

    
    
P4 PIER CAP IP

    
 
    
P2-P3 GIRDER STAGINGIP

    
    
P1 PIER CAP COMPLETE

    
    
EARTH FILLING IP AT CHERUVATHUR SIDE FOR SERVICE ROAD

    
 
 
 

 

 

 

 

 

 

 