   Weekly Progress Report as on 27.01.2012
    
Sl.No Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Pile at Kanjipura side 30 30 -- -- -- -- -- --
2 pile at Kuttipuram side 33 10 23   5 6   5
3 Pile cap at Kanjipura side 10 8 2 2 2 -- 2 2
4 Pier at Kanjipura side 9 8 1   1   1 2
5 PierCap at Kanjipura side 9 -- 9 -- 2 2 -- 2
6 PierCap at Kuttipuram side 10 -- 10 -- -- -- -- --
                   
Date 21/01/2012 23/01/2012 24/01/2012 25/01/2012 26/01/2012 27/01/2012      
Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant      
No. of labours 42 42 42 42 42 42      
                   
                   
Availability of Materials                
                   
Material Required Available              
Fine aggregate 45m3 20m3              
Coarse Aggregate 90m3 50m3              
Cement 650 bags 700 bags              
Steel 7MT 5 MT              
                   
                   
 
Back
 
    
PILE P7B

    
    
PILE P2A

    
    
PIERCAP P17

      
 

 

 

 

 

 

 

 