|
Pier cap (Total no of pier Cap- 21) |
Completed |
21 NOS COMPLETED |
|
RE Wall panel casting ( total600 nos) |
Completed |
|
|
Slab calicut side (total 10 nos ) |
In progress |
9nos done (adjacent span pending ) |
|
slab NH side ( 11 nos) |
In progress |
10nos done (adjacent span pending ) |
|
Retaining wall NH side |
In progress |
Done LHS 100%, RHS- 100% |
|
Dirt wall AP2 concreting |
In progress |
Done 100% |
|
Dirt wall AP1 concreting |
In progress |
Done 90% |
|
Handrail casting |
In progress |
1300 nos completed. |
|
Handrail fixing |
In progress |
NH side 10 slab completed. |
|
Handrail fixing |
In progress |
CALICUT side 8 span over. |
|
Boring at RP4 & RP1 |
Completed |
PILING COMPLETED |
|
Boring at RP3 |
In progress |
2-PILE CONCRETED |
|
Boring at RP2 |
In progress |
RP-2 ONE pile concreted. |
|
NH side RE panel erection |
In progress |
100% completed. |
|
RE wall work calicut side. |
In progress |
75% completed. |
|
expansion joint |
In progress |
AP1 balance |
|
painting-slab |
In progress |
calicut side 2 slab balance.(slab bottom only.) |