Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 8046200
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 27.01.2012
    
SlNo Activity –which can be completed without caution  Total Quantity Cumulative progress up to this week  Balance  work  Cumulative delay in weeks after  Work  planned  during the week  Actual work done during the last week  Short fall in the last week   Work   No of days remaining for completion as per the weekly plan Remarks
Description -1 -2 Spplagmnt  -4 -5 -6 Planned for next week 
      -3       -7
1 Re wall towards NH side 100% 34 66 32     0 0  0 .
3 Approach  5 5 0 37 - - - -    
 Span 
4 Pier cap 2 2 0 46  0  0  0  0  0   
5 Pile (Rly)pulikakadavu side 4 4 0 60  0  0 0  
6 Pile (Rly)Nh side 4 4 0 60 0 0 0 0 0  
6 Piers (Rly)  2 2 0 51  0  0  0  0    
9 R0AD WORK  100% 90 0              
{WBM} towards pulikkakadavu side
                       
1O Kerb/handrail  (approach portion)N.H side 200m Inner kerb concreting complete for a distance of  25 metres.Handrail posts  concreted for a. distance of 50 metres.No work in the last week.   Nil            
12 Friction slab  approach portion(N.H side 200m  No work in the last week                     
 
 
Back
 
    
SUCCESSFUL ATTEMPT TO LIFT CHISEL AT P7B1

    
    
PILING WORK OF P7B1 FOR BORING

    
    
BORING OF THE PILE P7,B5 IN HARD ROCK

      
 

 

 

 

 

 

 

 

Untitled Document