Prevoius Weekly Reports

   Weekly progress report as on 20.01.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE CHERUVATHOOR  SIDE

27

23

4

2

2

1

2

2

 

 

2

PILE PADANNA SIDE

24

21

3

3

0

0

3

0

 

 

3

PILE CAP CHERUVATHOOR SIDE

9

7

2

0

0

0

0

1

 

 

4

PILE CAP  PADANNA SIDE

8

6

2

0

1

1

0

0

 

P1 Pile cap complete

5

PIER CHERUVATHOOR SIDE

9

6

3

0

0

0

0

0

 

 

6

PIER PADANNA SIDE

8

3

5

2

1

0.5

3

2

 

P5 and P6 Pier fist lift complete

7

PIER CAP CHERUVATHOOR SIDE

9

5

4

0

1

0

1

0

 

 

8

PIER CAP PADANNA SIDE

8

2

6

0

0

0

0

1

 

 

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

RE panel casting to start this week

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

2

7

0

1

1

0

1

 

P14-P13 girder and slab complete

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0.5

 

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

  

 

Availbility of Men               
Date 13-01-2012 14-01-2012 15-01-2012 16-01-2012 17-01-2012 18-01-2012 19-01-2012
No of labours 57 57 57 57 57 57 57 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 750 1000
Steel(MT) 15 25 

 

 

Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1 to be shifted.P10 shifting complete
KSEB in progress estimation yet to be received,P1 and P10 location cleared.
KWA currently can be managed at site        
 
Back
 
    
STAGING STARTED FOR P2-P3 GIRDER

    
    
STAGING IP FOR P13-P12 GIRDER

    
    
P4 PILE CAP COMPLETE

    
    
CONCRETING OF P1 PILE CAP

    
 
    
CONCRETING OF DECK SLAB P14-P13

    
    
BSNL CABLE SHIFTING AT P10 LOCATION

    
    
AP2-P15 AND P15-P14 SPAN COMPLETE

    
 
 
 

 

 

 

 

 

 

 