   Weekly progress report as on 20.01.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week 
1 PILE THRIKKARIPUR  SIDE 33 33 Completed
2 PILE EZHIMALA SIDE 27 27 Completed
3 PILE PAYYANNUR SIDE 27 27 Completed
4 PILE CAP THRIKKARIPUR  SIDE 11 11 Completed
5 PILE CAP EZHIMALA SIDE 9 9 Completed
6 PILE CAP PAYYANNUR SIDE 9 9 Completed
9 PIER THRIKKARIPUR  SIDE 11 11 Completed
8 PIER EZHIMALA SIDE 9 9 Completed
9 PIER PAYYANNUR SIDE 9 9 Completed
10 PIER CAP THRIKKARIPUR  SIDE 11 11 Completed
11 PIER CAP EZHIMALA SIDE 9 9 Completed
12 PIER CAP PAYYANNUR SIDE 9 9 Completed
16 RE/R WALL THRIKKARIPUR  SIDE 100% 100% Completed
17 RE/R WALL EZHIMALA SIDE 100% 100% Completed
18 RE/R WALL PAYYANNUR SIDE 100% 70% 30% 30 10.00% 10.00% 10.00% 20.00%
28 BEAM/SLAB THRIKKARIPUR  SIDE 10 10 Completed
29 BEAM/SLAB EZHIMALA SIDE 7 7 Completed
30 BEAM/SLAB PAYYANNUR SIDE 10 8 Completed
31 HR/FP/KERB THRIKKARIPUR  SIDE 100% 100% Completed
32 HR/FP/KERB EZHIMALA SIDE 100% 100% Completed
33 HR/FP/KERB PAYYANNUR SIDE 100% 100% 0% 0 0.00% 0.00% 0.00% 0.00%
34 PAINTING 100% 20% 80% 0 5.00% 5.00% 0.00% 10.00%
35 BM 100% 15% 85% 0 40.00% 5.00% 35.00% 40.00%
36 BC 100% 0% 100% 0 0.00% 0.00% 0.00% 20.00% 

 

 

Availbility of Men               
Date 14-01-2012 15-01-2012 16-01-2012 17-01-2012 18-01-2012 19-01-2012 20-01-2012
Nof labours 50 50 50 50 50 50 50 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) available  
Fine Aggreagate(m3) available  
Cement(bag) 200 400
Steel(MT) 5

 

Utility shifting  
Utilities to be shifted Status
BSNL completed
KSEB completed
KWA completed
Others completed 
 