ROB at Koratty
Details of work done between 14th to 19th Dec 09.
PROGRESS AS ON 19-12-2009 |
Work Planned upto 19.12.2009 |
Completed/Progress |
Delay |
P4-P5 Span Staging work |
In progress |
|
Reinforcement work for I Girder |
In progress |
|
Approval of GAD by railways- follow up to be |
|
Delay in GAD approval |
done by contractor |
|
|
Box culvert reinforcement works |
In progress |
Delay by the contractor in starting
under pass
|
|