   Weekly progress report as on 20.01.2012
    
Progress Report - ROB-Thirunavaya
Sl.No  Activity Description Total Quantity Cumulative Progress upto last week Balance work up to last week Cumulative delay in Qty up to last week Work planned during the week Actual work done during the week Cumulative delay in Qty up to this week Work planned for the next week
1 Pile at Kanjipura side 30 30 -- -- -- -- -- --
2 pile at Kuttipuram side 33 5 28 2 5 5 1 5
3 Pile cap at Kanjipura side 10 8 2 2 2 -- 2 2
4 Pier at Kanjipura side 9 3 6 -- 2 5 -- 1
                   
                   
  Date 14/01/2012 15/01/2012 16/01/2012 17/01/2012 18/01/2012 19/01/2012 20/01/2012  
  Climate Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant Pleasant  
  No. of labours 38 38 38 38 38 38 38  
                   
  Availability of Materials                
                   
  Material Required Available            
  Fine aggregate 40m3 14m3            
  Coarse Aggregate 80m3 80m3            
  Cement 700 bags 1100 bags            
  Steel 6 MT 10 MT            
 