Prevoius Weekly Reports

   Weekly progress report as on 20.01.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto last week  Balance  work up to last week Cumulative delay in Qty up to last week Work  planned  during the week  Actual work done during the week  Cumulative delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks   
1 PILE  CALICUT  SIDE 48 48 0 0 0 0 1 0      
2 PILE THIRUR SIDE 24 23 1 0 2 1 11 2      
3 PILE CAP CALICUT  SIDE 12 12 0 0 0 0 1 0      
4 PILE CAP  THIRURSIDE 6 3 3 0 1 0 2 1      
5 PIER CALICUT SIDE 12 12 0 0 1 0 1 0      
6 PIER THIRUR SIDE 6 3 3 0 0 1 0 0      
7 PIER CAPCALICUT   SIDE 12 11 1 0 1 0 2 1   staging @ p5,p6 completed  
8 PIER CAP THIRUR SIDE 6 0 6 0 0 0 0 0      
9 RE/R WALL CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
10 RE/R WALLTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
11 BEAM/SLAB CALICUT   SIDE 12 0 12 0 0 0 0 0      
12 BEAM/SLAB THIRUR SIDE 6 0 6 0 0 0 0 0      
13 HR/FP/KERB CALICUT   SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
14 HR/FP/KERBTHIRUR SIDE 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
15 BC/PAINTING 100% 0 100% 0 0.00% 0.00% 0.00% 0.00%      
16 Deck Slab                      
17 Utility shifting                      
                         
                         
                         
  Availbility of Men                     
  Date 14-01-2012 15-01-2012 16-01-2012 17-01-2012 18-01-2012 19-01-2012          
  Nof labours 42 42 42 42 42 43          
                         
  Material Stocking Status Required Available Remarks                
  Coarse Aggreagate (m3) 28 21                  
  Fine Aggreagate(m3) 18 10                  
  Cement(bag) 450 190                  
  Steel(MT)   16                  
                         
                         
  Utility shifting                      
  Utilities to be shifted Status Remarks                  
  BSNL shifting completed                    
  KSEB shifting in progress                    
  KWA shifting completed                    
  Others                      
 
Back
 
    
STAGIN FOR PIERCAP P13

    
    
REINFORCEMENT FOR PIER @ P15

    
    
PILING @ P16

    
    
PEDESTAL CONCRETE @ P7

    
 
 
 

 

 

 

 

 

 

 