   Weekly progress report as on 20.01.2012
    
Si No  Activity Description  Total Quantity Cumulative progress upto 19.01.12 Balance  work up to 19.01.12 Cumulative delay in Qty up to 19.01.12 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week  No of days remaing for completion as per the weekly plan Remarks 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0 kwa line to be shifted KWA line to be shifted. Will be over by 18.01.12. work in progress.
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 14 28 0 5 7 -2 9    
4 PILE vytilla side(railway portion) 6 1 5 0 1 0 1 0   RP1 P4 done . RP1 P5 was abandoned due to pile choking. 
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0 kwa line to be shifted KWA line to be shifted. Will be over by 18.01.12. work in progress.
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 2 "      "  
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0   A2, P15, P14, P13,  P12,  P11, P10 
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0 "      "  
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0 "      "  
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 2 2   P15, P14, A2, P13, P12, P11, P10
14 GIRDER Palarivattom side(Approach portion) 7 5 2 0 1 1 0 0   A2 P15,P15 P14,P14 P13, P13 P12, P11 P10
15 DECK SLAB Palarivattom side(Approach portion) 7 2 5 0 1 1 0 1   A2 P15, P15 P14, 
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0    
17 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0    
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0    
19 RE WALL PANEL 355 355 0 0 0 1 0 0 0  

 

 

Labour Report              
               
Date 13.01.12 14.01.12 15.01.12 16.01.12 17.01.12 18.01.12 19.01.12
Day Fri Sat Sun Mon Tue Wed Thurs
Climate sunny  sunny  sunny  sunny  sunny  sunny   sunny 
No.of labours 85 90 38 91 90 69 107
               
               
Availability of Material               
               
Materials Required for week ending on 26.01.12 Available as on 20.01.12          
Fine aggregate(M3) Ready Mix Concrete          
Coarse aggregate(M3)          
Cement(BAG)          
Steel(TONN) 19 67          
               
 
Back
 
    
STRESSING P12 P13

    
    
PILE AT P2P2

    
    
GIRDER P10P11

    
    
DECK SLAB P14P15

    
 
 
 

 

 

 

 

 

 

 