Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7888279
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 20.01.2012
    
  Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
  RE Wall panel casting ( total600 nos) Completed  
  Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
  slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
  Retaining wall NH side In progress Done LHS 100%, RHS- 100%
  Dirt wall AP2 concreting  In progress Done 100%
  Dirt wall AP1 concreting  In progress Done 90%
  Handrail casting In progress 1200 nos completed.
  Handrail fixing In progress NH side 10 slab completed.
  Handrail fixing In progress CALICUT side 8 span over.
  Boring at RP4 & RP1 Completed PILING COMPLETED
  Boring at RP3 In progress 2-PILE CONCRETED
  Boring at RP2 In progress RP-2 ONE pile concreted.
  NH side RE panel erection In progress 100% completed.
  RE wall WORK. In progress 75% completed.
  expansion joint completed In progress AP1 balance
 
Back
 
    
ROAD WORK -NH SIDE.

    
    
RE WALL WORK IN PROGRESS AP2 SIDE.

    
    
PILING WORK IN RP2-3.

    
    
PAINTING WORK IN PROGRESS.

    
 
 
 

 

 

 

 

 

 

 

Untitled Document