   Weekly progress report as on 20.01.2012
    
SlNo   Total Quantity Cumulative progress up to this week  Balance  work  Cumulative delay in weeks after  Work  planned  during the week  Actual work done during the last week  Short fall in the last week   Work   No of days remaining for completion as per the weekly plan Remarks
Description     Spplagmnt        Planned for next week 
               
1 Re wall towards NH side 100% 34 66 32     0 0  0 .
3 Approach  5 5 0 37 - - - -    
 Span 
4 Pier cap 2 2 0 46  0  0  0  0  0   
5 Pile (Rly)pulikakadavu side 4 4 0 60  0  0 0  
6 Pile (Rly)Nh side 4 4 0 60 0 0 0 0 0  
6 Piers (Rly)  2 2 0 51  0  0  0  0    
9 R0AD WORK  100% 90 0              
{WBM} towards pulikkakadavu side
                       
1O Kerb/handrail  (approach portion)N.H side 200m Inner kerb concreting complete for a distance of  25 metres.Handrail posts  concreted for a. distance of 50 metres.No work in the last week.   Nil            
12 Friction slab  approach portion(N.H side 200m  No work in the last week                     
 
 
Back
 
    
CONCRETING OF THE PILE P7B4 USING BOOM PUMP

    
    
CAGE LOWERING OF THE PILE P7B4

    
    
CAGE LOWERING OF THE PILE P7B4

    
    
BORING OF THE PILE P7B4

    
 
    
BORING OF PILE P7B4

    
    