|
Name of Project |
Airport Seaport Road Phase II Section A - Package 1 |
|
Location |
HMT to NAD |
|
District |
Ernakulam |
|
Contract value of the work |
35.07 crores |
|
SPV |
Roads and Bridges Development Corporation of Kerala Ltd |
|
Project Management Consultant and Supervision |
KITCO |
|
Funding |
Government |
|
Right of Way |
45m |
|
Length including approaches |
2.7 Km |
|
Contractor |
M/s RS Developers & Constructions India (P) Ltd |
|
Agreement Date |
23.11.2015 |
|
Date of NTP issued |
24.11.2015 |
|
Commencement of Project |
24.11.2015 |
|
Scheduled date of Completion |
23.11.2016 |
|
Current Status |
The project has been delayed due to the non availability of HMT and NAD land. In the available stretch 90% of subgrade has been completed
60% GSB and WMM has been completed |