Name of Project Airport Seaport Road Phase II Section A - Package 1
Location  HMT to NAD
District  Ernakulam
Contract value of the work 35.07 crores
SPV Roads and Bridges Development Corporation of Kerala Ltd
Project Management Consultant and Supervision KITCO
Funding  Government
Right of Way 45m
Length including approaches 2.7 Km
Contractor M/s RS Developers & Constructions India (P) Ltd
Agreement Date 23.11.2015
Date of NTP issued 24.11.2015
Commencement of Project 24.11.2015
Scheduled date of Completion 23.11.2016
Current Status The project has been delayed due to the non availability of HMT and NAD land. In the available stretch 90% of subgrade has been completed
60%  GSB and WMM has been completed
 

 

 

 

 

 

 

 

 

 