Untitled Document
Road to Prosperity
Site last updated on:  12-12-2020 | You are visitor: 7887008
Completed Projects Projects Under Construction Citizen Services Careers Right to Service


Prevoius Weekly Reports

   Weekly progress report as on 13.01.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE Muthambi side

27

18

9

0

0

0

0

0

 

2

PILE Thamarassery side

33

30

3

0

0

0

0

0

 

3

PILE NH SIDE

30

22

8

0

2

2

0

3

 

4

PILE CAP Muthambi SIDE

9

5

4

0

1

1

0

0

 

5

PILE CAP Thamarassery SIDE

11

0

11

0

4

0

4

4

 

6

PILE CAP NH SIDE

10

7

3

0

0

0

0

1

 

7

PIER Muthambi  SIDE

9

5

4

0

0

0

0

1

 

8

PIER Thamarassery SIDE

11

0

11

0

0

0

0

3

 

9

PIER NH SIDE

10

7

3

0

0

0

0

0

 

10

PIER CAP Muthambi  SIDE

9

4

5

0

1

1

0

1

Work in progress.

11

PIER CAP Thamarassery SIDE

11

0

11

0

0

0

0

0

 

12

PIER CAP NH SIDE

10

0

10

0

2

2

0

2

 

13

RE/R WALL Muthambi side

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

14

RE/R WALL Thamarassery side SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

15

RE/R WALL NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

16

BEAM/SLAB Muthambi SIDE

8

0

8

2

2

1

1

2

P13-P14 girder reinforcement in progress.

17

BEAM/SLAB Thamarassery SIDE

10

0

10

0

0

0

0

0

 

18

BEAM/SLAB NH SIDE

11

0

11

0

0

0

0

0

 

19

HR/FP/KERB Muthambi SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

20

HR/FP/KERB thamarassery SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

21

HR/FP/KERB NH SIDE

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

22

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0

0.00%

 

23

Utility shifting

 

 

 

 

 

 

0

 

KSEB utility shifting started. Shifted 1 post 

 

Availbility of Men               
Date 01-07-2012 01-08-2012 01-09-2012 01-10-2012 01-11-2012 01-12-2012 13/1/2012
Nof labours 62 75 70 70 65 65 75 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) 100 120
Fine Aggreagate(m3) 100 120
Cement(bag) 1200 1800
Steel(MT) 18 25 

 

 
Back
 
    
PILE P7 B

    
    
P14-P15

    
    
P6 PIER

      
 

 

 

 

 

 

 

 

Untitled Document