Progress Report For ROB Puliyanam for the week ending on 13/01/2012 |
Sl No |
Activity Description |
Total Quantity |
Cumulative progress upto last week |
Balance work up to last week |
Cumulative delay in Qty up to last week |
Work planned during the week |
Actual work done during the week |
Cumulative delay in Qty up to this week |
Work Planned for next week |
Remarks |
1 |
Pile towards NH side |
26 |
26 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
2 |
Pile towards Puliyanam side |
18 |
18 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
3 |
Pile cap at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
4 |
Pile Cap at Puliyanamside |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
5 |
RC wall at Puliyanam side |
100% |
85% |
15% |
0 |
0% |
5% |
0% |
5% |
|
6 |
RC wall at NH side |
100% |
75% |
25% |
0 |
0% |
5% |
0% |
5% |
|
7 |
Pier at NH Side |
6 |
6 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
8 |
Pier at Puliyanam Side |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
9 |
Piercap at NH Side |
6 |
6 |
0 |
0 |
0 |
1 |
0 |
0 |
TARGET ACHIEVED |
10 |
Piercap at Puliyanam |
4 |
4 |
0 |
0 |
0 |
0 |
0 |
0 |
TARGET ACHIEVED |
11 |
PEDESTAL |
54 |
45 |
9 |
9 |
0 |
0 |
9 |
9 |
|
12 |
Beam and cross beam at NH side |
6 |
2 |
4 |
0 |
0 |
1 |
0 |
0 |
|
13 |
Beam and cross beam at Puliyanam side |
4 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
|
14 |
Deck slab at NH side |
6 |
1 |
5 |
0 |
0 |
0 |
0 |
0 |
|
15 |
Deck slab at Puliyanam side |
4 |
0 |
4 |
0 |
0 |
0 |
0 |
0 |
|