   Weekly progress report as on 13.01.2012
    
Pier cap (Total no of pier Cap- 21) Completed 21 NOS COMPLETED
RE Wall panel casting ( total600 nos) Completed  
Slab calicut side  (total 10 nos ) In progress 9nos done  (adjacent span pending )
slab NH side ( 11 nos) In progress 10nos done  (adjacent span pending )
Retaining wall NH side In progress Done LHS 100%, RHS- 100%
Dirt wall AP2 concreting  In progress Done 100%
Dirt wall AP1 concreting  In progress Done 90%
Handrail casting In progress 1100 nos completed.
Handrail fixing In progress NH side 10 slab completed.
Handrail fixing In progress CALICUT side 8 span over.
Boring at RP4 Completed RP-4 FOUR pile concreted.
Boring at RP3 In progress 2-PILE CONCRETED
Boring at RP1 Completed RP-1 FOUR pile concreted.
NH side RE panel erection In progress 100% completed.
RE wall WORK. In progress 50% completed.
expansion joint completed In progress AP1 balance
 
Back
 
    
SHUTTERING & RFT WORK OF RETAINING WALL BRAKET.

    
    
RAILWAY PORTION WORK IN PROGRESS.

    
    
PILE CONCRETING RP3-6.

    
    
P.C.C. FOR FRICTION SLAB.

    
 
    
HANDRAIL WORK.

    
    
BORING IN RP3-6.

      
 

 

 

 

 

 

 

 