   Weekly progress report as on 13.01.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

Remarks

1

PILE CHERUVATHOOR  SIDE

27

21

6

2

2

2

3

2

 

2

PILE PADANNA SIDE

24

21

3

2

0

0

3

0

 

3

PILE CAP CHERUVATHOOR SIDE

9

7

2

0

0

0

0

0

 

4

PILE CAP  PADANNA SIDE

8

5

3

1

1

1

1

1

P4 Pile cap complete

5

PIER CHERUVATHOOR SIDE

9

6

3

0

0

0

0

0

 

6

PIER PADANNA SIDE

8

2.5

5.5

2

2

0

3

1

P5 Pier fist lift complete

7

PIER CAP CHERUVATHOOR SIDE

9

5

4

0

0

0

1

1

 

8

PIER CAP PADANNA SIDE

8

1

7

0

1

1

0

0

P3 Pier cap complete

9

RE/R WALL CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

10

RE/R WALL PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

RE panel casting to start this week

11

BEAM/SLAB CHERUVATHOOR  SIDE

9

2

7

0

1

0

1

1

P14-P13 girder reinforcement works 90% complete

12

BEAM/SLAB PADANNA SIDE

8

0

8

0

0

0

0

0

 

13

HR/FP/KERB CHERUVATHOOR  SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

14

HR/FP/KERB PADANNA SIDE

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

  

 

Availbility of Men             
Date 07-01-2012 08-01-2012 09-01-2012 10-01-2012 11-01-2012 12-01-2012
No of labours 51 38 51 51 51 51 

 

Material Stocking Status Required Available
Coarse Aggreagate (m3) shortage of 12 mm at the site  
Fine Aggreagate(m3) available  
Cement(bag) 800 1000
Steel(MT) 15 20 

 

Utility shifting        
Utilities to be shifted Status Remarks    
BSNL AP1,P10 to be shifted.P10 shifting in progress
KSEB in progress estimation yet to be received,P1 and P10 location cleared.
KWA currently can be managed at site       
Others         

 

 
Back
 
    
P9 LOCATION

    
    
P4 PILE CAP COMPLETE

    
    
P3 PIER BEAM COMPLETE

    
    
P2 PIER BEAM COMPLETE

    
 
    
CONCRETING OF P9 B PILE

      
 

 

 

 

 

 

 

 