Prevoius Weekly Reports

   Weekly progress report as on 13.01.2012
    
 

Si No

Activity Description

Total Quantity

Cumulative progress upto last week

Balance  work up to last week

Cumulative delay in Qty up to last week

Work  planned  during the week

Actual work done during the week

Cumulative delay in Qty up to this week

Work  Planned for next week

No of days remaing for completion as per the weekly plan

Remarks

1

PILE SHORNUR  SIDE

9

9

 

 

 

Completed

 

 

 

2

PILE M.C SIDE

36

36

 

 

 

Completed

 

 

 

 

3

PILE CAP SHORNUR SIDE

3

3

 

 

 

Completed

 

 

 

 

4

PILE CAP  M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

5

PIER SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

6

PIER M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

7

PIER CAP SHORNUR  SIDE

3

3

 

 

 

Completed

 

 

 

 

8

PIER CAP M.C SIDE

12

12

 

 

 

Completed

 

 

 

 

9

RCC WALL SHORNUR SIDE

100%

58

42%

0

15.00%

3.00%

63.00%

22.00%

0

Concreting of RCC wall completed on both sides.Filling and rolling of soil completed.Reinforcement work and shuttering  of cornice and outer kerb in RCC wall

10

RE/R WALL M.C SIDE

100%

55

45%

0

15.00%

1.00%

13.00%

22.00%

0

RE wall erection and rolling completed for all layers.Coping beam work  shuttering completed on 9-1-2012.No cement stock at the site to do the concreting.All the remaining works are pending due to cement shortage

11

BEAM/SLAB SHORNUR SIDE

3

2

1

0

0

0

0

0

0

 

12

BEAM/SLAB M.C SIDE

12

11

1

0

1

1

0

0

0

.Therefore deshuttering work of all spans (beam and deck slab) completed..PAINTING WORK WILL COMMENCE ON 12-1-2012

13

HR/FP/KERB SHORNUR  SIDE

100%

62

38%

0

0.00%

0.00%

0.00%

0.00%

0 days

footpath slab(cast in situ) setting completed.Due to non availability of cement concreting cannot be done

14

HR/FP/KERB M.C SIDE

100%

57

43%

0

10.00%

5.00%

6.00%

10.00%

 

.Footpath slab concreting completed in 11 spans.Precast footpath slabs setting completed

15

BC/PAINTING

100%

0

100%

0

0.00%

0.00%

0.00%

0.00%

 

painting will commence on 12-1-2012

16

Deck Slab

 

 

 

 

 

 

 

 

 

 

17

Utility shifting

 

 

 

 

 

 

 

 

 

 

18

RCC WALL M.C SIDE

100%

0

100

 

25.00%

8.00%

 

30.00%

 

RCC WALL earthwork excavation for foundation is completed on both sides of the RCC Wall on 8-1-2012.Even the PCC could not be done because there is no cement at the site. 

 

Availbility of Men             
Date 01-07-2012 01-08-2012 01-09-2012 01-10-2012 11.1.2012 01-12-2012
Nof labours 22 22 20 20 22 24 

 

Material Stocking Status        
  Required Available Remarks  
Fine aggregate {cft} 300 400    
Cement(bag) 450 0 stock wil be replendished today  
Steel inT 6.5 7    
Coarse Aggreagate (cft) 300 350     

 

Utility shifting  
Utilities to be shifted  
BSNL COMPLETED
KSEB COMPLETED
KWA COMPLETED
Others COMPLETED 

 

 