   weekly progress 12.01.2012
    

 

Revised Progress Report For Ponnurunni ROB for the week ending on 12.01.12
Si No  Activity Description  Total Quantity Cumulative progress upto 12.01.12 Balance  work up to 12.01.12 Cumulative delay in Qty up to 12.01.12 Work  planned  during the week  Actual work done during the week  delay in Qty up to this week Work  Planned for next week 
1 PILE  Palarivattom side(Approach portion) 31 28 3 0 0 0 0 0
2 PILE Palarivattom side(railway portion) 6 0 6 0 0 0 0 0
3 PILE vytilla side(Approach portion) 42 7 35 0 5 5 0 7
4 PILE vytilla side(railway portion) 6 1 5 0 1 0 1 0
5 PILE CAP Palarivattom side(Approach portion) 8 7 1 1 1 1 0 0
6 PILE CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
7 PILE CAP vytilla side(Approach portion) 9 0 9 0 0 0 0 0
8 PILE CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
9 PIER Palarivattom side(Approach portion) 8 7 1 0 3 1 0 0
10 PIER Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
11 PIER Vytilla side(Approach portion) 9 0 9 0 0 0 0 0
12 PIER vytilla side(railway portion) 1 0 1 0 0 0 0 0
13 PIER  CAP Palarivattom side(Approach portion) 8 7 1 0 0 0 2 2
14 GIRDER Palarivattom side(Approach portion) 7 4 3 0 1 1 0 0
15 DECK SLAB Palarivattom side(Approach portion) 7 1 6 0 0 0 0 1
16 PIER CAP Palarivattomside(railway portion) 1 0 1 0 0 0 0 0
17 PIER CAP  Vytilla side(Approach portion) 9 0 9 0 0 0 0 0
18 PIER CAP vytilla side(railway portion) 1 0 1 0 0 0 0 0
19 RE WALL PANEL 355 355 0 0 0 1 0
 
Back
 
    
WINCH SHIFTING RP1 TO P8

    
    
STRESSING P14P13

    
    
KWA PIPE RELAYING.

    
    
CONCRETING P4P2

    
 
    
CONCRETING P1P2

    
    
CAGE LOWERING RP1 P5

      
 

 

 

 

 

 

 

 