Weekly progress report as on 06.01.2012 |
|
|
Service road on kanjippuram side |
Completed |
for piling. |
|
Piling |
In progress |
Completed 32 nos |
|
Pile cap |
In progress |
Completed 8 nos(P11,P12,P13,P14,P15,P16,P17,P18) |
|
Reinforcement for Pile cap P14 |
In progress |
|
|
Load testing for P19 a |
completed |
|
|
Pier |
In progress |
P11 1st lift |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Back |
|
PILE P 10 A
|
| | |
PILE P10 B
|
| | |
PILE CAP P 17
|
| | |
PILE CAP P18
|
| | |
| |
|
|