Work Planned upto 9/1/2010 |
Completed / Progress |
Remarks |
P4-P5 Span Staging work |
Completed |
|
Reinforcement work for I Girders |
In progress |
|
Profiling for 1 No. Girder & shuttering |
Completed |
|
Approval of GAD by railways- follow up to be |
|
Delay in GAD approval |
done by contractor |
|
|
Box culvert works |
Not started |
Delay by the contractor in starting under pass |