ROB at Bakel
PROGRESS OF ROB WORK AS ON 04.09.2010 |
Description |
Completed/ Progress |
Remarks |
Span on Kasargod side |
|
|
Hand rail casting |
In progress |
Slow progress due to heavy rains |
Span on Kannur Side |
|
|
Concreting of 1 no beam |
Completed |
|
Shuttering work for 2 nos beams |
Progress |
Road Blocked on 24.07.2010 |
|